Compton
/
OSP
/
How to
/
T. Pussieux
Procedure 9
How to switch the chicane on after a shutdown ?
This procedure is only performed by MCC operators.
First of all,
the Hall A Run Coordinator must request that MCC tune the beam through the Compton chicane.
MCC operators have to apply the section 2 of the procedure MCC-PR-04-001. If necessary (after a long shutdown for exemple), let's remind to the operator to open valves located on the Compton line.
The complete procedure is available on the MCC web site at :
http://opsntsrv.acc.jlab.org/ops_docs/online_document_files/MCC_online_files/HallA_beam_delivery_proc.pdf
Compton Polarimeter
last updated : 06/11/2004
Procedure 9
CEA 1995 - all rights reserved