I will be at the meeting this morning, but in the interest of speeding my part I wanted to send my contribution out a little early: Target Update for 7/20/2005 What has been accomplished: Heater line in place -- new filter system in place -- heaters connected to pipes -- heaters connected to controllers -- controllers have been checked out Temporary Oven in Place -- temporary windows installed -- flange to connect to old set up machined, fired and installed -- blank ready to be installed to test oven -- mounted old cell (Vega) in place -- low polarization -- short lifetime -- ice cone cell NMR system nearly ready to go: -- Need new coils (damaged in preparing to install) -- Should be ready this afternoon Laser system: -- laser installed and in interlock -- temporary mirrors nearly installed Necessary for Signal: -- Check out oven (run with blank in place), this afternoon -- Change over to cell, tonight or tomorrow -- Put polaraized light on cell (per Ameya) -- measure signal (need good coils, but then all I need is a signal) Necessary for August 1 milestone: -- Mount GEn cell in new flange (get cell from Gordon or Todd) -- Prefer small chamber (currently using small optics) -- Assemble and mount new oven -- To meet the milestone we MUST have the new oven as soon as possible. -- Anything else? Thanks, Aidan