7/27/2005 Alan presents diagram of proposed beamline. He discusses the question of how to couple to beam dump. It is suggested that the material for the supports of the beamline be G10 rather than aluminum or stainless steel. Todd suggests that an explosion test can be done using the proposed dimensions and discusses the production of the explosion chamber to be used during the experiment. Bodo talks about the test run of the drift chambers. The chambers responded well in the sense that the current drain was stable. The highest luminosity used was a factor of ~8 lower than the experiment will use. Luminosity scans were done as well as high voltage scans and the current drain scaled with both luminosity as well as applied voltage. There exists a problem with the front end electrnics which limits data acquisition: When the multi-hit TDC's record too many hits, the memory is filled resulting in an overflow error. The result is that all 128 channels of the TDC no longer pass data to the DAQ. It is difficult to pinpoint which channel causes the overflow, complicating the diagnostics of the problem. However, Bodo suggests that data should be observed in the test lab in order to begin resolving the problem. This problem resulted in the loss of around half the TDC's at the highest rates during the test run. Bogdan briefly discusses the direction of data analysis to use data taken with the lead-glass plus scintillator trigger to calculate rates per wire. He also mentions the apparent difference in effective efficiencies between pre-amplifier cards. The observation is that the distribution of data among the wires is not uniform as expected (when using the double-scintillator trigger) but has "jumps" between sections of 16 channels. The effect is not as dramatic at lower voltages (1400 V) and the cause is still not understood. He suggests a special meeting between those involved to discuss this question perhaps near the middle of next week. Albert presents progress on the neutron arm. Last week, wiring of the cassettes was begun. More than 60% of the cabling is connected to the detector, but not to the front end electronics. Scaffolding is needed to complete this task. Timing cables will be moved into the test lab within the week to begin their preparation. Todd is able to offer the work of 2 graduate students for a couple of days each to help with the cabling projects. Jacob has completed the connection of the signal cables both to the shower counter as well as the front end. High voltage and timing cables still need to be installed and extra manpower would be useful in this project. Aidan plans to attempt polarizing a cell tomorrow. It would be the first cell polarized in this holding field. He has recently recieved the jig which mounts the cell and requires a GEn geometry cell, possibly to be provided by UVa. The group from the UVa target lab plans to come here to install the optics in order to teach Ameya and Aidan. Plans are made to install all existing optics while waiting for the last 6" mirror to arrive (~ 4 - 6 weeks.) It may be possible to begin polarizing cells using an existing 4" mirror. There is a discussion about the possible use of a "track" system using multiple small breadboards to mount the optics rather than purchasing and waiting for the delivery of a single large breadboard. Vladimir has the news that a cell was cracked while being filled at UVa last week. It may still be possible to use the cell as a water cell for water calibration. Ameya will report next week on his progress in measuring the magnetic field direction using both a compass as well as a Hall probe.