PVDIS Run Plan Oct-Dec, 2009
DRAFT
last updated: 11/06/09, 2:38pm

General Information:  draft calendar.
Go to today's run plan.


Things to do during commissioning (in preliminary order), including person in charge, [estimated beam time], and planned time:


  • To do: MCC nulls the vertical polarization [2 hours]
  • To do: Mini-spin dance to tune wien angle. Require coordinate with MCC and Hall B in advance - (Sasha) [3 points, up to 6 hours]
  • To do: Moller commissioning (injector work) - Sasha with injector people [3 hours]
  • To do: fix carbon optics position???
  • To do: bcm calibration (invasive to Hall B, not coordinated yet!) for both HAPPEX copies and PVDIS copies (brief version?), with empty target - Kai, Rupesh, Xiaoyan [time? 2-4 hours? Must be done when the beam is relatively stable]
  • If the DAQ is working:


  • Things to do periodically:
    Things to do once during the whole period:
    Expert list:
    Overall:
    What we should keep an eye on: Meetings: