PREX TEST PLAN
This file: hallaweb.jlab.org/experiment/HAPPEX/prextest.html R. Michaels, Nov 2005
The following tables show a time ordered list of the measurements including things not directly related to PREX for the last day of HAPPEX with the usual priorities "Must", "Should", "Like". At the moment the plans add to 22 hours, which implies starting at 10 AM. We must stop at 08:00 on Tues Nov 21. If the schedule starts to slide, we reject lower priority items.
Plan | Priority | Duration | People |
Modify BPMs, adjust ion chamber trips | Must | 2 hours | CASA(BPM), Radcon(IC) |
Low current monitor commissioning | Must | 1 hour | CASA, R. Michaels |
LH2 runs with low current | Should | 1 hour | R. Michaels |
Low pressure LH2 (Alum. Wall check) | Must | 2 hours | D. Meekins, B. Moffit |
Pass Change to 1-Pass Meanwhile cool target. | Must | 2 hours | MCC |
Alignment and low-I checks | Must | 1 hour | R. Michaels |
C12 and Alum targets ("calibration") | Like (maybe) | 1 hour | R. Michaels |
Quartz profile scans, Rate checks. | Must | 2 hours | K. Paschke, L. Kaufman |
Install UMass PREX detectors | Must | 2 hours | K. Paschke, B. Moffit |
Align UMass PREX detectors | Must | 1 hour | B. Moffit |
Ramp I to 4 uA, don't trip septa, regress, dither, see widths, etc | Must | 2 hours | K. Paschke, L. Kaufman |
Repeat previous step without S0, time permitting | Like | 2 hours | K. Paschke, L.Kaufman |
Ramp up current until septa trip. HAPPEX DAQ | Must | 1 hours | K. Paschke, L. Kaufman |
High current (5 to 80 uA), Lumi data, check if melts | Should | 2 hours | R. Michaels |