Transversity Collaboration Meeting

(May.04, 2007 at JLab L102/104)

 9:00-9:15    Hall A status and schedule. -- Kees de Jager

 9:15-9:30    Milestone check and discussions. -- Xiaodong Jiang (.pdf)

 9:30-9:50    BigBite hardware items for transversity. -- Doug Higinbotham

 9:50-10:05   BigBite preshower block work. -- Albert Shahinyan (.pdf) (.ps) (.ps) (.ps) (.ps)

 10:05-10:30    BigBite gas Cherenkov hardware progress. -- Brad Sawatzky (.pdf)

 10:30-10:45    Chamber-2 work at UVa. -- Nilanga Liyanage

 10:45-11:00     --Short break--

 11:00-11:30   Trigger/DAQ and shower block test. -- Kalyan Allada (.pdf)

 11:30-12:00    BigBite wire chamber ch1+ch3 test,and A Monte Carlo tool for wire chamber tracking.-- Xin Qian (.pdf)

 12:00-12:30    Software progress, wire-chamber tracking. -- Ole Hansen (.pdf)

 12:30-13:30    --Lunch break--

 13:30-13:45    Decisions on HRS Aerogel detector. -- Lingyan Zhu(.ppt)

 13:45-14:00    Progress and decisions on HRS RICH detector. -- Evaristo Cisbani (.pdf)

 14:00-14:20    BigBite design item specifications and priorities.-- Xiaodong Jiang

 14:20-14:50    Polarized target design progress. -- Al Gavalya

 14:50-15:00   Target discussions, cell production. -- Todd Averett

 15:00-15:20   Target lab update. -- Chiranjib Dutta (.ppt)

 15:20-15:35   --Short break--

 15:35-16:45   Planning for summer work at JLab:
           1. BigBite hardware work in the Hall.
           2. BigBite magnetic shielding piece and fringe field measurement.
           3. Target lab work, vertical coils..
           4. Test Lab work, BigBite detector test.
           5. HRS Aerogel detector work.
           6. HRS S2M related checkout/work.

 16:45-17:30  Discussion of manpower/responsibility and collaboration issues.

 17:30    Adjourn