keyword=Run Plan for Swing 10/2 - Day 10/3
The run plan for the next 24 hours will be:
Complete Moller commissioning run for today (nominally 8PM)
Test BPM/raster calibrations in regards to work done this morning
Compton commissioning runs (directed by Alex, carried out by Eric)
Calorimeter anode current test runs (directed by Alex or his designee)
Multiharp scan (MCC directed), crew of at least 2 must be present in CH
Transition to controlled access for work in the morning
The assigned crews for these shifts have been placed on standby. Phone
numbers to contact all of them are on the whiteboard. Carlos has agreed
to act as shift leader for the program after Moller and is responsible
for calling them in when deemed necessary to carry out the program.
A copy of this log entry has been emailed to: riordan, munoz, camsonne