    User name riordan

    Log entry time 17:18:46 on October 03, 2010

    Entry number 333526

    keyword=Run Plan for Swing 10/3 through Day 10/4

    Significant progress on cooling down the magnets have been made and we should be ready to cool down the target tomorrow. This process should take about 24 hours once started. Since magnets are now cold we can have Jack start getting the power supplies online. Alex did some work on the BPMs and the saturation problem appears to have been fixed.

    Plans for the next 24 hours:
    Once the target is cooling/has cooled, target operators must be on shift, regardless of if we are taking beam or not. I will send out announcements to the collaboration once this is firm. It is my plan to stay open during the day each day until Jack has completed all power supply work.

    Work to be scheduled: