keyword=Run Plan for Swing 10/3 through Day 10/4
Significant progress on cooling down the magnets have been made and we
should be ready to cool down the target tomorrow. This process should
take about 24 hours once started. Since magnets are now cold we can have
Jack start getting the power supplies online. Alex did some work on the
BPMs and the saturation problem appears to have been fixed.
Plans for the next 24 hours:
- Moller commissioning for swing shift
- BPM/raster calibration
- Multiharp scan (MCC directed)
- We will stay in beam permit overnight
- 07:00 we will start a BCM calibration
- After BCM calibration, open hall to restricted (to be confirmed by
Ed)
- Work in the hall tomorrow:
- Magnet power supplies
- Target cooldown (needs to be scheduled)
- Additional cryo work by Heidi et al.
Once the target is cooling/has cooled, target operators must be on shift,
regardless of if we are taking beam or not. I will send out
announcements to the collaboration once this is firm. It is my plan to
stay open during the day each day until Jack has completed all power
supply work.
Work to be scheduled:
- Compton Tuning (tentatively Monday swing)
- Arc energy measurement (Tuesday swing?)
- One more shift of Moller commissioning
- HRS commissioning/optics