Log entry time 11:39:02 on October 05, 2010
Entry number 333713
keyword=Run Plan for Swing 10/5 through Day 10/6
We are continuing to work on power supplies in the hall. JP is in the
process of cooling down the target. MCC is retuning the machine to
deliver beam of the appropriate energy (they are 10 MeV high for 5 pass).
Plans for the next 24 hours:
- Let techs work as long as they need
- Compton tuning (if retuning complete)
- Calorimeter current anode tests
- Collect HRS detector data with beam if dipole is ready
- 07:00 we will open the hall to restricted for techs
When the target is cold, cryo-target operators are required to be on
shift, regardless if it is in standby or not.
Since we cannot use spot++ because we have no physics trigger, I'm
limiting runs to no raster on BeO (for spot check) and carbon targets.
Work to be scheduled:
- BCM calibration, when hall B goes down for detector
reconfiguration
- One more shift of Moller commissioning
- HRS commissioning/optics
- Arc energy (early next week?)