    keyword=Run Plan for Swing 10/6 through Day 10/7

    We spent more time on the power supplies in the hall and are making progress. We can run the dipole overnight and we can put beam on the cryotarget, so we can start our next phase of commissioning.

    Plans for the next 24 hours:
    Qweak is planning a hot checkout tonight and will start cooling down the target tomorrow late morning/afternoon. This has a potential to affect our hall.

    Work to be scheduled: