    Swing Shift Summary

    16:00 Production run on LH2 15 cm with 2uA
    Starting with Run # 8069 , 173K events
    22:03 One of the arc magnets tripped
    23:10 Beam recovery, harp scan is OK
    23:21 Production run on LH2 15 cm with 2 uA
    Run # 8077
    23:59 Total ~ 6 h 40 min production run