    keyword=Shift summary for 11-08 owl

    Shift crew:
    SL: Eric FUCHEY;
    TO: Hoyoung KANG;
    3rd: Hyekoo KANG.

    12:00 am: continue DVCS production, compton data taking has been stopped (wild rates);
    1:30 am: beam trip which last almost 25 minutes;
    4:55 am: issue with daq, some nboards were not initialized; redownload the config solved the problem;
    Other than these minor incidents everything goes well till 8:00 am.

    Runlist:
    8469: LH2 15 cm, 3 uA, PS5 = 1, DVCS production;
    8470: LH2 15 cm, 3 uA, PS5 = 1, DVCS production;
    8471: LH2 15 cm, 3 uA, PS5 = 1, DVCS production;
    8472: LH2 15 cm, 0 uA, PS5 = 1, Pedestal run (almost 25 minutes beam trip);
    8473: LH2 15 cm, 3 uA, PS5 = 1, DVCS production;
    8474: LH2 15 cm, 3 uA, PS5 = 1, DVCS production;
    8475: LH2 15 cm, 3 uA, PS5 = 1, DVCS production;
    8476: LH2 15 cm, 3 uA, PS5 = 1, DVCS production;
    8477: LH2 15 cm, 3 uA, PS5 = 1, DVCS production;
    8478: LH2 15 cm, 3 uA, PS5 = 1, DVCS production.