User name horn
Log entry time 16:03:10 on December 3,2010
Entry number 342586
keyword=Day shift summary
DAY SHIFT 3 DECEMBER 2010
SL: T. Horn, TO: R. Michaels
SHORT SUMMARY
Took production data with beam through compton chicane. At end of shift asked MCC to switch tune to straight through.
DETAILED SUMMARY
8:00 MCC still working on RF issues from earlier this morning
8:20 Beam back. Resume data taking (KIN 3, p0=2.59 GeV/c, theta0=21.5 deg)
9:45 BPMA beam positions drifting to about +0.35 in X and to about +0.25 in Y during run 9215, MCC resets energy lock/FB and adjusts beam positions. Beam positions on BPMA back to about zero in X and Y at end of run 9215
10:20 Started run 9216 with BPMA positions of (+0.07,+0.04)
12:30 Beam gone for Qweak tests in Hall C, taking a pedestal run (9218)
12:50 Resume production data taking
15:40 Changing tune from through beam through compton chicane to straight through
15:55 Start run 9222 with straight running tune
RUN SUMMARY
Run Events BCM U3 D3 (C) Time Avg Curr Deadtime
9214 1022 k 0.01032 0.01032 60.6 mins 2.8395 uA 16.25%
9215 1211 k 0.00997 0.00998 59.7 mins 2.7853 uA 21.19%
9216 1033 k 60 mins 2.8 (no end run)
9217 1265 k 0.00935 0.00934 56.1 mins 2.7784 uA 23.18%
9218 15 k 0.00002 0.00000 12.1 mins 0.0175 uA 4.70%
9219 1290 k 0.00974 0.00975 59.8 mins 2.7147 uA 23.32%
9220 1244 k 0.00944 0.00946 59.7 mins 2.6380 uA 29.52%
9221 968 k 0.00724 0.00721 45.9 mins 2.6245 uA 25.12%