    User name jpchen

    Log entry time 16:02:07 on December 6,2010

    Entry number 343048

    keyword=day shift summary


    Day shift summary

    Shift workers: J. P. Chen (SL), H. Yao (TO), R. de Leo (3rd)

    8:00 target loop 2 (LH2) fan not working, in controlled access,
    J. P. tried reset and power cycle the controller earlier. Still not working.
    Now Dave Meekins is working on it: swap controller with loop3.
    8:20 Dave Meekins used loop 3 fan controller for loop2 and it worked.
    called for beam
    8:40 Resume data taking on LH2 at kin2-high
    9:50 moved to LD2, taking data on LD2 at kin2_high.
    16:00 still take production data on LD2 at kin2_high.

    Run Events BCM U3 D3 (C) Time Avg Curr Deadtime
    9292 1260 k 0.00640 0.00641 67.2 mins 1.5884 uA 18.22%
    9293 1540 k 0.00428 0.00427 68.3 mins 1.0423 uA 23.77%
    9294 1498 k 0.00419 0.00416 65.0 mins 1.0696 uA 19.78%
    9295 1548 k 0.00430 0.00430 69.4 mins 1.0325 uA 22.67%
    9296 1488 k 0.00414 0.00412 69.6 mins 0.9893 uA 18.54%
    9297 1674 k 0.00465 0.00462 78.4 mins 0.9860 uA 23.25%