    User name Holmstrom

    Log entry time 16:07:46 on December17,2010

    Entry number 344858

    keyword=Day SHift Summary

    8:00 Shift starts with beam on target.

    9:50 Switch to D2 running.

    12:00 Cryo flow to Hall C stops, which causes a rise in our temperatures. The target warms up and needs to be cooled. Beam off to fix problem. J. P. Chen helping us.

    12:40 Moving to Optics target while the target recovers.

    12:53 Loop 1 has recovered so we are moving back.

    13:03 Return to production.

    13:21 DVCS IOC crashed. Rebooted.

    16:00 SHift Ends with beam on target

    Runs
    9730 4109 k 0.01247 0.01200 60.9 mins 3.3478 uA ~25%
    9731 1732 k 0.00263 0.00251 15.7 mins 2.7263 uA
    9732 6501 k 0.00979 0.00933 59.1 mins 2.6955 uA
    9735 323 k 0.00049 0.00047 2.9 mins 2.7788 uA
    9738 5731 k 0.00865 0.00830 52.4 mins 2.6949 uA
    9739 441 k 0.00086 0.00082 12.2 mins 1.1431 uA
    9740 2004 k 0.00306 0.00291 17.7 mins 2.8200 uA ~28%
    9741 5499 k 0.00836 0.00801 60.3 mins 2.2630 uA
    9742 6556 k 0.01008 0.00963 59.0 mins 2.7844 uA ~29%