    User name jpchen

    Log entry time 16:22:00 on December20,2011

    Entry number 361203

    keyword=shift summary

    Day shift summary

    shift workers: J. P. Chen (SL), F. Wessselmann (2nd), X. Zheng (3rd)
    experts help: M. Huang, A. Camsonne, J. Liu.

    8:00 continue optics @ -1% magnet +1%).
    Found fast raster was on. It was on for all the previou
    optics runs (-4%, -3%, -2%, -1%) (was called +4...+1% for magnet settings.
    Then 0%.
    At 0% did septum field (current) scan (475A, 455A, 435A).

    After that, Alexandre did a harp scan (10:30), it did not work.
    (Later MCC tried ioc reboot, not working, Michelle (software group) is investigating.)
    11:00 BCM/calorimeter calibration (alexnadre and company)
    12:30 back out of BCM calibration. There are problems with BCM readout. Back to optics run
    +1%. then 2%, 3%, 4%.
    14:55 Complete optics scan.
    Requested controlled access for BCM/supreharp investigation.
    Parasitic test access to chane gas bottle.

    15:05 started controlled access.
    16:00 still in access. Most work completed.