Log entry time 06:07:18 on December 22, 2011
Entry number 361742
This entry is a followup to: 361733
keyword=Owl shift summary
0:00 Q1 current study: +5%, -5%
0:43 Continue with low current BCM test scan @ 80nA, 100nA, 120nA, 150nA,
200nA, 500nA, 1uA.
1:49 Continue with Q1 study, scan from 10% to 50%, finally set @ 30%.
Then Q2 study, runs @ -5% and -2%, set @ -2%. Last but not least, Q3
study, runs@ -5%, +5%, -2%.
4:07 Continue with a few other beam current scan. Then turned rasters ON.
Detailed information in Pengjia's halog as referred.
6:00 Beam OFF. Commissioning completed. YaY