    User name kelleher

    Log entry time 10:00:01 on February 22, 2012

    Entry number 362286

    Followups:

    keyword=RC report

    This is a modified version of the report that I gave at the Hall A meeting on Tuesday Feb 21

    Work done over the past week: Target cold, ramped, and have polarized a target at 5T

    Septum shims are installed local dump is installed (waiting on a survey to close up target area)

    DAQ has recovered from power mixup (although we are looking for and testing spares)

    Still to be done:

    Align beamline -- yesterday, the achieved the 0 position alignment, then moved the beamline through its positions. Currently attaching bellows for final alignment with and without vacuum.