This is a modified version of the report that I gave at the Hall A meeting on Tuesday Feb 21
Work done over the past week: Target cold, ramped, and have polarized a target at 5T
Septum shims are installed local dump is installed (waiting on a survey to close up target area)
DAQ has recovered from power mixup (although we are looking for and testing spares)
Still to be done:
Align beamline -- yesterday, the achieved the 0 position alignment, then moved the beamline through its positions. Currently attaching bellows for final alignment with and without vacuum.