    User name pzhu

    Log entry time 08:45:52 on April 07, 2012

    Entry number 371117

    keyword=owl shift summary

    1:50 done for 1.931GeV/c, start to do dilution for this setting 2:25 done for dilution, move target back NH3, Changed the momentum to 1.294 2:35 left arm momentum is locked, start to take production run for 1.294 4:00 MFZ1H05B magnet tripped, mcc are trying to fix it 4:20 mcc asked for controlled access to fix the FZ magnet 4:40 target magnet ramped down for mcc people to go to the target area 5:10 hall status go back to beam permit, target magnet is ramping up 5:25 ready for beam, check beam position again 5:40 beam position didn't changed ,moved back NH3 for production 5:45 start for production 8:07 finished 1.294 production, start dilution 8:37 finished dilution, changed momentum to 1.203