Here is the run plan for owl shift: Keep taking data for 0.541 and 0.504 with 60nA. When finish these 2 points, set both HRS to 1.859 GeV. Make sure to change beam current back to 50 nA and change the prescale for T1 and T3. Run left HRS while right dipole is ramping. The goal is to take 160M events, which might take up to 5 hours. At 8:30 shift leader will ask for restricted access.
During restricted access, the chicane will be moved. Pengjia and Chao will fix right BCM. Vince, Ryan and Melissa will check T2 again. Target group will do another anneal and some TE, might also replace target material if needed. After changing the chicane tomorrow, we need to test the harp, do bpm calibration, then take optics data, then continue taking production data. Karl need to provide detail run plan and post it in the wiki.