User name Chao
Log entry time 08:02:56 on April10,2012
Entry number 372477
keyword=Owl shift summary
Shift Workers:
Chao Gu(SL), Pengjia Zhu(TO), Eric Jensen(3rd)
00:00 Shift start with no septa and no beam.
00:00 Looks like the septa can not be fixed tonight. Pengjia will start to do some beamline test once the beam is back.
02:30 MCC start to tune beam into the hall.
04:00 MCC mentioned they have a beam quality issue, they will try to fix it.
07:15 Beam is back. Pengjia start to do some slow raster calibration.
08:00 Pengjia finished the slow raster calibration. He is doing harp scan now. We will ask control access at around 8:30 to fix the septa issue.