User name jmaxwell
Log entry time 17:49:22 on April 11, 2012
Entry number 372802
keyword=Status Update, Tonight's Plan
Thanks to the hard work of Jack and the Hall A techs, the Right Septum is
again operational, albeit at reduced maximum current. It was tested to
800A.
Jack was finished around 16:30 and we called for a sweep to close up the
hall after the pivot sweep was finished by the target experts, around
17:00. The sweep is proceeding, after which we will move on with
bringing beam back into the hall to do optics. The optics run will
require low helium level, so the target expert will keep an eye on the
start of the optics running.
Optics will likely take up deep into Owl shift, when we can move on with
the production run plan.
Day overview:
18:00 - 0:00 (last night): Moller
0:00 - 6:30: BCM, BPM, Harp
6:30 - 8:00: Sweep of hall for restricted access
8:00 - 16:30: Septum work
16:30 - Now: Sweep to close hall