    keyword=production runplan for 1.7 GeV

    The production runplan for the upcoming day is posted

    The right arm should be set to 1.589 GeV/c as soon as optics is complete. The first setting in the Table (4M events at Po=1.691 GeV/c) should be taken with left arm only, then proceed to the 1.589 GeV/c setting with both arms.

    Prescalers listed in the table are rough guidance only. Adjust to get optimal rate with <25% deadtime.



    A copy of this log entry has been emailed to: james.davis.maxwell@gmail.com,mcummings422@gmail.com,boeglinw@fiu.edu, jpchen@jlab.org