Make Followup Entry
User name jmaxwell
Log entry time 17:52:12 on April 17, 2012
Entry number 375941
keyword=Status, Plan for Tonight
The hall is being swept and we are well into our TE measurement. Once
the TE is done, we will start bringing beam into the hall and center the
beam on the Hole target and set the raster size. The beam current for
all the following tasks is 10nA!
Once we have the beam centered, we can go ahead with optics. We'll need
some optics on carbon and on ammonia; Jixie is in charge of this. The
target operator should start polarizing once we move to take optics on
the ammonia target. The optics will run with the slow raster on; we'll
do at least 20 minutes on Carbon 40 and 20 minutes on ammonia. Jixie may
change this a bit.
Once the optics are done, we'll need an access to take out the sieve.
Then ensure the slow raster is on and start with GEp production:
Both HRS at 1.6910 GeV/c, Left Septum at 533.416 A, Right Septum at
705.257 A, beam current 10nA.