    keyword=optics plan for gep at 1.706 GeV

    Here is the optics plan for gep at 1.706 GeV:
    P0=1.691
    
    Sieve IN:
    target   config                   number of events or beam  time
    C12    Sieve IN, No rasters      2 x 1M (10 minutes)
    C12    Sieve IN, Both rasters    2 x 1M (10 min)
    NH3    Sieve IN, Both rasters    3 x 7M (about 1 hours, which will give
    about 400 events  when cut to 1x1 beam size, refer to Min Huang's halog
    for details)
    Escort access to move sieve out (30 min)
    C12    Sieve out, both rasters   30 minutes(about 10 M events for each
    arm, good for dilution)  
    
    In total 2.5 ABU,  3 hours were allocated.