    Summary

    00:10 Beam Position Scan Done. Acceptance study Part I started.

    00:40 Acceptance study part I finished. Delta scan started.

    03:40 Delta scan done. Student expert tested the rasters while R-HRS settling.

    04:30 Pointing study finished. Asked MCC for escorted access to move the sieve out.

    05:00 Sieve out.

    05:20 Beam back. Acceptance study part II. Energy has shifted from 1.151 to 1.157 GeV.

    05:40 Optics Done. Move to production(R) / Packing fraction(L). Taking bottom cell.

    06:05 L-HRS VDC HV tripped during the configuration change. Recovered.

    06:30 Left Septum tripped and not recovering. We are running

    07:45 Asked for access to reset L-Septum.

    08:00 Waiting for access.