    keyword=Production from 8-10, beam off 10-12.

    Day shift started with continue production at P0=0.6596 GeV/c.
    Target polarization dropped to about 26%, beam polarization measure last even was 89%.
    Scaled events needed is 114*(84/89*31/26)**2=144M.
    We got 137M.