    keyword=optics plan for 2.254GeV with 5T and 0 deg target field

    
     Here is the optics plan for 2.254GeV with 5T and 0 deg target field.
     Before doing optics, beam center and slow raster size have to be determined.
     
     No LHe, LHRS starts at 0% and right HRS start at 4%:
     
     1. Delta scan:  C12, sieve in , no raster  (3 hours)
     Left HRS: -4%, -3%, -2%, -1%, 0%, 1%, 2%, 3%, 4%
     Right HRS: 4% (Right septum I<=920A, so can only go to 4%.)
    (-4%, -1% and +3% can be ignored if running out of time) 
     NOTE: if possible, do 3% for right arm, which is 930A.
     
      
     **Ramp left dipoles back to 0% when finish. (40 minutes)
     
     2. Beam position scan: C12, delta=0; sieve in, slow raster only,  (40
    minutes)
     Config the slow raster to jump in the following way:
     1)between (x=-5, y=-5) and (5,5)
     2)between x=0, y=+/-5
     3)between x=+/-5, y=0
     
     
     3. Acceptance calibration, part 1:  C12, sieve in, delta=0  (10 minutes)
     1) both rasters on
     
     4. Pointing: CH2, sieve in ,delta=0, no rasters (30 minutes)
     Take data till the H peak of a normal sieve hole can be fit.
     
     **Escorted access to move sieve out when finish (30 minutes)
     5. Acceptance calibration, part2:  C12, sieve out, delta=0 (20 minutes)
     1) no rasters
     2) both rasters
     
     
     Estimated time: 7 hours
     
     At the end of the optics, refill LHe, change to the 1st production point,
     start dilution runs then polarize NH3 target.