Here is the optics plan for 2.254GeV with 5T and 0 deg target field.
Before doing optics, beam center and slow raster size have to be determined.
No LHe, LHRS starts at 0% and right HRS start at 4%:
1. Delta scan: C12, sieve in , no raster (3 hours)
Left HRS: -4%, -3%, -2%, -1%, 0%, 1%, 2%, 3%, 4%
Right HRS: 4% (Right septum I<=920A, so can only go to 4%.)
(-4%, -1% and +3% can be ignored if running out of time)
NOTE: if possible, do 3% for right arm, which is 930A.
**Ramp left dipoles back to 0% when finish. (40 minutes)
2. Beam position scan: C12, delta=0; sieve in, slow raster only, (40
minutes)
Config the slow raster to jump in the following way:
1)between (x=-5, y=-5) and (5,5)
2)between x=0, y=+/-5
3)between x=+/-5, y=0
3. Acceptance calibration, part 1: C12, sieve in, delta=0 (10 minutes)
1) both rasters on
4. Pointing: CH2, sieve in ,delta=0, no rasters (30 minutes)
Take data till the H peak of a normal sieve hole can be fit.
**Escorted access to move sieve out when finish (30 minutes)
5. Acceptance calibration, part2: C12, sieve out, delta=0 (20 minutes)
1) no rasters
2) both rasters
Estimated time: 7 hours
At the end of the optics, refill LHe, change to the 1st production point,