Log entry time 15:55:32 on May14,2012
Entry number 384896
keyword=Day shift summary
We spent almost the whole shift on beam pass change, target anneal and TE measurements. The hall was in restricted access during most of the shift.
15:00 Change both HRS momenta to 2.2017 GeV/c. Right arm Q2 and Q3 cycled.
15:10 Left HRS momentum is ready. Both Septa are ready. Right arm dipole is on-going, and Right Q2 and Q3 are being cycled.
15:25 Beam permit, target moved to Home/empty for beam tune.
16:00 We are just waiting for the beam.