Minutes of Hall A Group Meeting July 15, 2008
1)
Installation:
(Ed Folts)
a)
Target
foil supports are in position
b)
Chamber
support is in place
c)
Hadron
Detector went up today
d)
Wire
Chamber to be installed by the end of the week
e)
Working
on motion mechanism controls
f)
Working
on Power supply upgrades
g)
Q3
has been de-stung
h)
Re
He leak test: we used a lot less He than expected. We are off the hook for the
time being.
2)
Al
Gavalya:
a)
Had
a meeting last week with alignment re Compton installation. Joyce is working
with them.
b)
Susan
continues with Polarized 3He work.
c)
Macon
will return to us on September 17, 2008.
d)
Al
owes J-P cost to completion for Transversity
e)
Work
continues on PREX magnet. Pavel is doing simulations.
3)
Bert
Manzlak:
a)
Last
week senior management was presented
with the results of the ISM assessment
i)
4
major positive attributes
ii)
3
weaknesses
iii)
Final
report to the lab in August
iv)
We
have the highest marks of labs looked at so far
4)
Doug
Higinbotham:
a)
Gas
Čerenkov is the last major issue re BigBite detectors
i)
Hall
B has agreed to test our gas bottle
ii)
Cosmic
ray testing is ongoing
5)
Alexandre
Camsonne:
a)
Just
back from Clermont-Ferrand. Where he worked on the Compton electron detector
i)
Electron
detector to be shipped next week
b)
Working
on new version of ARS(?)
c)
Will
discuss installation of DVCS calorimeter with Doug.
6)
Ole
Hansen:
a)
Counting
House Computer upgrade is in progress. Should be done by the end of the week.
7)
Vince
Sulkosky:
a)
Albert
found the missing S2m cables. They were in Warwick Storage
b)
Ensuring
that S2m electronics are in place
c)
Continuing
work with summer student re GDH background analysis
8)
J-P
Chen:
a)
Polarized
3He instrumentation moving to the Counting House
b)
Checking
on cabling needs
c)
Cell
characterization continues
i)
Analyzing
data to find optimal running conditions
d)
NIM
paper re Polarized 3He? J-P agrees one should be written.
9)
Bob
Michaels:
a)
Preparing
for HAPPEX/PREX meeting next week
b)
Testing
18-bit ADC’s (Qweak vs. ours, they’re about the same)
c)
There’s
a missing custom CAMAC amplifier. It has “S2 EDT” in its name. If you know
anything about it please contact Bob (rom@jlab.org)
10)
Sirish
Nanda:
a)
Compton:
i)
Had
a meeting with Neil Wilson and Chris Curtis re electron detector installation.
(1)
Overall
looks OK
(2)
Neil
checked things in the Hall and has one issue re the hoist. He has some
alternate ideas (to be discussed)
ii)
Working
on MOU with ODU
11)
Bogdan
Wojtsekhowski:
a)
Testing
of A1 is going well
i)
Some
equipment is missing (from the cleanup).
ii)
Finishing
early next week, then ready to install
b)
Trieste
proceedings submitted
c)
RCS
paper in preparation
d)
Making
progress with Super BigBite
12)
Eugene
Chudakov:
a)
Re
Møller upgrade:
i)
Paul
has identified pieces that can be ordered
ii)
Design
needs to be done for long lead items
13)
John
LeRose:
a)
Checked
on problem noted last May with NMR probe A on the left HRS. Vacuum box is
opened and we are ready to go inside the magnet to service the probe if needed.
Found that the probe, with no field, no longer exhibits the problem noted in
May (see halog 241951). Since the magnet is currently warm we
can’t test the probe with field. Will leave the vacuum box open and retest with
field when the magnet is cold.
-JJL