| 0000 | 0100 | 0200 | 0300 | 0400 | 0500 | 0600 | 0700 | Total Time | |
|---|---|---|---|---|---|---|---|---|---|
| Acceptable Beam in Use | 30 | 50 | 1 | 30 | 1 | 40 | 1 | 1 | 6.5 |
| Beam Available but Not in Use | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Beam Not Available or Unacceptable | 30 | 10 | 0 | 30 | 0 | 20 | 0 | 0 | 1.5 |
| Accelerator Con- figuration Chage | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Experiment Ready | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 8 |
| Planned Config- uration Change | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Unplanned Experiment Down | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Hall not ready reasons | |||||||||
| Target | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| HRSe | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| HRSh | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Data Acq | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Other | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Comments: Ran with different hall tune (see HALOG) since midnight because target was boiling slightly due to the coil pulsing slope and the raster size... Need to do more tests (altering raster size, intensity, and CoilP slope) to achieve an optimal (non boiling, high intensity) configuration. No major problems all night - injector DAQ was down for 1/2 hour.
Data Entry by: Relyea