    Entry number 19774

    keyword=Beam Time Accounting
    Hall A

    5/3/1999 0800-1600
    Experiment #: E91-010
    Shift Leader: E. Chudakov
    Shift Workers: G. Rutledge, P. Markowitz

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    15 10 60 40 60 60 60 60 6.08333333333333
    Beam Available
    but Not in Use
    0 50 0 0 0 0 0 0 0.833333333333333
    Beam Not Available
    or Unacceptable
    30 0 0 20 0 0 0 0 0.833333333333333
    Accelerator Con-
    figuration Chage
    15 0 0 0 0 0 0 0 0.25
    Experiment
    Ready
    45 60 60 60 60 60 60 60 7.75
    Planned Config-
    uration Change
    15 0 0 0 0 0 0 0 0.25
    Unplanned
    Experiment Down
    0 0 0 0 0 0 0 00
    Hall not
    ready reasons
    Target 0 0 0 0 0 0 0 0 0
    HRSe 0 0 0 0 0 0 0 0 0
    HRSh 0 0 0 0 0 0 0 0 0
    Data Acq 0 0 0 0 0 0 0 0 0
    Other 0 0 0 0 0 0 0 0 0

    Comments: 0830: MCC had trouble tuning in the moller settings 0950: Moller beam established. 1115: Moller finished, Happex tune and settings requested. 1130: MCC is sending 2uA for a raster check, then we will resume HAPPEX.

    Data Entry by: G. Rutledge