Meeting held at JLab in room 16/84 from 10am to 12am
with:
Hakob, Eugene, Bogdan, Alan, David and Franck
Report
-
RTV cookie/mold: The ideal meniscus radius seems to be 24". Hakob
thinks it's better to make a smaller cookie, then stick it to the PMT once
it's fully dry. Also we can fill the space between the edges of the PMT
and the cookie with RTV (using a tape for instance) to get an even better
optical coupling. We will try that out and make the mold for the 25 piece
prototype.
-
Pb-glass radiation damage: As planned, David has done a new measurement
on the block that was damage. The results are consistent with what Hakob
found in the first place. Also, he tried to cure it with UV lamp and no
significant effect has been found on a short time scale. We will repeat
the test on a longer time scale. Bogdan has installed three blocks (which
transmissions have been measured) at 30, 60 and 180 degrees of the beam
line, at about 3 to 4 meters of the target to estimate the radiation damage.
The blocks are more or less at the level of the beam line. The 180 degree
block is under the beam line. At the next maintenance day, the transmission
of those blocks will be measured again.
-
9/25-block prototype: Hakob has got all the mechanical parts. he
glued the titanium flanges on the Pb-glass blocks with epoxy and made some
resistance tests. It seems it can resist at least 20 kg of traction
(about a factor two more than what we apply with the string). The bases
for the phototubes are not ready yet, but will be shortly. Also, we have
to think about the block wrapping, using aluminized mylar and tedlar (?).
There are still discussions on the need for single-side aluminized mylar
or double-side. If we use the single-side aluminized mylar, which side
do we put against the glass. In any case, the prototype has to be light-tight.
-
Database for the calorimeter: We have discussed the possibility
to have a complete database of the blocks/bases/phototubes, using either
numbers on tags or bar codes. The bar code solution might be smarter considering
the high number of items to be entered in the database.
-
Misc. issues: Alan wants us to keep in mind that we need all the
parts for the whole calorimeter (750 pieces) before the summer to be able
to get summer students to work on it. The titanium flanges might take quite
a long time to arrive. Also, there has been discussions whether JLab could
order and pay the parts with Illinois' money (transfered on some local
account) or not. Alan will see if it's possible to transfer the $63k to
JLab. We would then create an account for which Eugene would be responsible
for. Also let us keep in mind that hakob will leave in 2 to 3 weeks. We
need to learn everything he has been working on in the meantime.
-
Schedule for the next few months: We have discussed a reasonnable
schedule till the end of the summer:
4/27 - 4/29
Maintenance days
|
Install the 9-block prototype in the Moller apparatus.Also install
a (4x4x10) cm3 lucide block and a similar scintillator
piece there |
5/8 - 5/10
Facility time
|
Request 4 hours of beam-time to test the 9-block prototype. Also compare
the lucide/scintillator VETO detectors |
5/11 - 5/13
Maintenance days
|
Install the VETO detectors (lucide/scintillator) in hall A for parasitic
comparison during HAPPEX data taking (5/14 - 5/28) |
5/14 - 5/28
HAPPEX
|
Parasitic comparison of the VETO detectors |
5/29 - 7/8
Shutdown
|
-
Prepare/install the 25-block prototype
-
Prepare/install the 6+6 VETO detectors
-
Prepare/install the MWPCs
-
Try to install the Fastbus DAQ electronics
|
7/9 - 7/30
HAPPEX
|
Parasitic data taking |
7/31 - 8/3
Commissioning
|
Request 2 shifts for test runs (similar to 1998 test runs) |
-
Other important dates:
-
05/20 - 05/22: Workshop on exclusive reactions at JLab
-
05/23 - 05/25: Hall A collaboration meeting
Franck Sabatie - 04/14/1999
PLEASE, fill free to mail any
remarks or advice to Franck Sabatie,
they will be transmitted and discussed at the next meeting.
maintained by Franck
Sabatie
|