Meeting held at JLab in room 16/84 from 10am to 11:30am
with:
Ting, Albert, Armen, Edward, Samuel, Bogdan, Eugene,
Charles and Franck
Report
-
Circuit boards: 600 boards are soldered on one side and 200 on both
sides. We've lost Clive who won't help us with that anymore. Charles will
try to get someone else to do the job.
-
Ti flange gluing: 88 flanges have been glued so far. The present
rate is 8/day. Several tests have been performed on all the glued
flanges to make sure the paralellness is good enough.
-
Sockets/pins gluing: 210 sockets are ready so far. The rate
is about 20/day.
-
DAQ: Ting reports on linearity/stability tests of the fastbus
ADCs. The results are satisfying. He will give actual linearity results
next week.
-
Mini-collaboration meeting: THe mini-collaboration meeting
is very likely to happen thursday next week all afternoon (starting at
2pm). We would review most of the RCS setup. I will send an email later
this week to set this up.
-
Wires/heat shrink tubing/springs: I've ordered the heat shrink
tubing, it will arrive within a week. The wires will be ordered soon, and
should arrive shortly too. The quotation for the springs is not back yet
but should be here shortly. Once reviewed, we will order the springs and
will get them 5 weeks later. We might want to ask for a small sample to
start with.