During the month of March the following will be: ---------------------------------------------------------- Calorimeter - complete the light box and HV interlock - complete 100 m signal cable bundles DAQ - complete the radiation test on Left Arm - installation DAQ platform infrastructure HV - complete the radiation test on Left Arm - repair of the main frames - production of the distribution boxes - production of the multi wire HV cables - test, preparation short HV cables Veto - test HV dividers - test of the counters by means of LED - installation of the light minitoring MWPC - design of the mounting Detector frame - construction in progress Magnet - design of the magnet Power supply - test plan development ========================================================== During the month of April the following will be: ---------------------------------------------------------- Calorimeter - prepare for installation on the Detector frame - development of the air supply for cooling Cable Arm - welding of the pivot to the Left Spectrometer HV - complete repair of the main frames - testing of the HV modules and cables - production of the distribution boxes - production of the multi wire HV cables Veto - installation of the HV dividers - installation of air cooling MWPC - construction of the mounting Detector frame - installation of the infrastructure - design of the lifting subframe Magnet - bidding process - design of the support stand Left Arm HRS - beam test for optimal optics for angular resolution ========================================================= During the month of May the following will be done: --------------------------------------------------------- Calorimeter - finishing construction and testing of the gain monitoring system - installation of pipe from outside to the Hall for supply clean air for PMT cooling Cable Arm - test installation HV - testing of the HV modules and cables - production of the distribution boxes - production of the multi wire HV cables Veto - testing of detectors one by one MWPC - prepare radiation test in the Hall A Detector frame - installation of the infrastructure - bidding for lifting subframe Magnet - construction - bidding for the support stand - design of the beam line shielding Survey - marks on the Hall A floor for Detector - marks on the Hall A floor for Magnet stand Power supply - prepare space, AC, control, and water in the Hall A Left Arm HRS - 4.3 GeV magnet test ========================================================= During the month of June the following will be done: ------------------------------------------------------ Calorimeter - final installation of the with optical grease PMTs - testing of the blocks one by one including front end electronics Cable - delays - move to the Test Lab - connection on the DAQ side Cable Arm - mounting of the cable trays on the Arm HV - testing of the cables - production of the distribution boxes - production of the multi wire HV cables Veto - installetion of the Detector frame MWPC - test of operation with beam in the Hall Detector frame - installation of the infrastructure - construction of lifting subframe Magnet - construction of the magnet - construction of the support stand - construction of beam line shield TOSP - document for the Detector - for the Magnet - for the DAQ - for the Cable Arm ========================================================== During the month of July the following will be done: ---------------------------------------------------------- Calorimeter - final installation of PMTs - testing of the blocks one by one including front end electronics - cosmic test with DAQ Cable - delays - move to the Test Lab - connection to Calorimeter and Veto HV - testing of the cables - production of the distribution boxes - production of the multi wire HV cables Veto - cosmic test with DAQ Detector frame - installation of the infrastructure Magnet - construction of the magnet - construction of the support stand - test of beam line shield efficiency Power supply - test of the power, control on the load ============================================================ During the month of August the following will be done: ------------------------------------------------------ Calorimeter - cosmic test with DAQ - prepare for move into Hall A Cable - delays - prepare for move into Hall A - HV - complete production and installation Veto - cosmic test with DAQ Detector frame - prepare for move into Hall A DAQ - prepare for move into Hall A Magnet - construction of the magnet - support stand delivery Power supply - prepare for move into Hall A - prepare the 1000 Amp cables, - prepare control, safety cables - prepare water cooling for magnet TOSP - approval by Kees and AD ============================================================ During the month of September the following will be done: ------------------------------------------------------------ Calorimeter - move to the Hall A - installation of Detector frame - connection to HV and DAQ - cosmic test Cable Arm - installation on the Left Spectrometer (*) Cable - delays - move into Hall A - installation on the Cable Arm (*) Veto - move to the Hall A - installation on the Detector frame - connection to HV and DAQ - cosmic test Detector frame - move into Hall A ( the Left side ) - installation detectors - installation of lifting subframe DAQ - move on the floor of left side of Hall A Power supply - move to the Hall A, installation - connection to AC, control, and water - test with BigBite as a load HRS detector - reconfiguration of Gas Cherenkov - installation of the front FPP - cosmic test, fixing FPP TOSP - team training ============================================================= During the month of October the following will be: ------------------------------------------------------------ Detector - analysis development DAQ - pulser tests - analysis development FPP - parasitic test on protons ============================================================ During the month of November the following will be: ------------------------------------------------------------ Detector - move to the Right side - connection cables on the Detector side - move according to the run plan Magnet - installation support stand - delivery of the magnet to the Hall A - installation on the support stand - installation safety net across gap - test magnetic fields - installation beam line shielding Initial part of the run plan - radiation on Detectors with magnet OFF/ON - calibration FPP systematics - adjustment of HV on ep events - calibration lead glass with MWPC - calibration of the electrons deflection ============================================================ During the month of December the following will be: ------------------------------------------------------------ Photon Spectrometer - according to the run plan ============================================================ During the month of January the following will be: ------------------------------------------------------------ Detector - disconnect from DAQ - move on the left side - conservation DAQ - disconnect from cable Arm - move on the floor on left side - conservation Cable Arm - remove cables, conservation - move out from Hall A, conservation Magnet - move out from Hall A, conservation ============================================================