SBS Weekly May 3, 2017 Present Riordan, Puckett, Annand, Cornejo, McClellan, Montgomery, N. Liyanage, Fuchey, Nelyubin, Katugampola Higinbotham, Camsonne, Liyanage, Wines, Wojtsethowski, Gnanvo, Monaghan, Kohl Agenda - ERR outline review Quinn Robin notes Jessie's estimate for installation is 6-8 months Will poll institutions on available manpower Jones Brings up issue of slow controls for magnets 48D48 must be controlled by ACC due to beamline steering Ole was to be physics liaison? Will add in scientific goals to detector status Wines Will have drawings complete by June 14 for beamline support Only few items left to complete for fabricating Still working out three scenarios for HCal support to show Original required decabling between moves Second was to buy floor plates to roll it around like SBS (favor option) Third option is for new exoskeltal frame to lift as unit (would require larger crate) Need to have meeting to discuss and choose option Franklin Drawings for support tied into finishing cabling gantry Needs additional support from JLab (crane operator) Averett Brian presents Todd's slides briefly Liyanage Will have gas system presentation May 10 Andrew will show GEM shielding hut calculation Monaghan Butler - Not available Target group - Not available Riordan Camsonne Needs to check luminosity numbers Need updated GEM rates Specifically add in accidentals for other systems for completeness Puckett Not clear on RSAD responsibility Radcon should provide table Eric is iterating with Doug, Al Gavalya, and Pavel Bogdan notes activation and exposure to beamline reconfigurations Needs to be requested from Radcon Dry runs will be May 12