- 12GeV preparation
- We want 15 cm loop (GMP wants 20cm). The other targets Alex
listed on ELOG
entry 108 are ok.
- LHRS repair with Bogdan: both Charles and Julie were contacted by
Bodgan with a request to help out in the upgrade/refurbishing of the LHRS. The work
described by Bogdan is upgrade of the electronic of the VDC and repair
of the Cerenkov. Both Charles and Julie said they will try to provide
a student (for Julie at the earliest in summer 2013).
- Charles plans to attend the GMP coll meet. The meeting in Monday
afternoon Sept 17, 2-6 pm. Charles plans to present a run plan.
- Miscellanous:
- 6 GeV analysis: Alejandro is still in vacation: no progress since last week.
- Alexandre is putting together a DOE early career proposal. He is
proposing to build a GEM based vertex detector to try to measure
Double DVCS. See: Elog 109
- The hall A CC met last week. The Winter Hall A meeting is
scheduled for Monday December 10 and Tuesday
December 11 with a software
workshop on Saturday December 8. Dates need to be comfirmed.
- Pion paper: Charles and Eric still need to talk.
|