Message ID: 3     Entry time: 06/11/04, 18:05
Author: Franck Sabatie 
Subject: Minutes of Installation meeting - 06/08/2004 
  Present: Ed Folts, Jack Segal, Sirish Nanda, Al Gavalya, Pierre Bertin,
Franck Sabatie.

  Minutes:

  Installation starts Aug 2nd (monday).

  Aug 2-8

    In the Hall:

        - Left and right HRS detector work (Jack)
        - FPP Rack dismount (Jack)
        - DVCS Patch Panel mount (Jack)

    In the EEL:

        - Detector uncabling (RG213) (us)
        - Clean up, ready up for moving cables, then detectors (us)

  Aug 9-15

        - Install DVCS Racks in left HRS hut
        - String one 25m (XY-table) cable to check where to put
        all slow control racks and HV. Then pick the location and
        install all that.
        - Ed can move the left HRS a bit away from beam line so that
        we can start stringing RG213.
        - At the end of the week, Septa are out.

  Aug 16-22

        - Install BigBite stand (some welding, machining, survey necessary)
        - Start install of scattering chamber.
        - DVCS team works on acquisition.

  Aug 23-29

        - Bring DVCS stand in.
        - Put DVCS stand on Big Bite stand (requires some welding,
        machining, survey, etc)

  Aug 30-Sept 6

        - Cabling (RG213, slow control, HV, ...) starts when DVCS stand is
        on place.

  Tests can begin with full detector as soon as cabling finished (which
should be fast. Should leave about 1week for tests before hall locked
period (Sept 10-20).

  Additional notes:

        - Large Cerenkov detector will be in left HRS.
        - Pion rejector might have bad blocks, needs to be checked with
        Eugene.