PVDIS Switchover Run Plan Oct. 29-Nov. 1, 2009
DRAFT
Run Coordinator: Paul Reimer
Cell phone: (757) 876-1787 Pager: (757) 584-5411
Things to do during switchover, including person in charge, [estimated time], and planned time. Note: almost
all items can be moved earlier or later depending on how fast we
proceed. Please keep in contact with others and the RC to facilitate
your work.
- Day (-7) - Day 0, 10/21-10/28
- Setup Shift Guide, organize webpage - Xiaochao, with help from others.
- Setup shift checklist and runsheets - Xiaochao.
- Software setup (person in charge should also write how-to's for shift-takers and offliners)
- Set up Podd Analysis framework - Ramesh, Vince, Jin, Kai.
- include online GUI from standard HRS experiments and our June test run GUIs, right?
- in-shift
prompt analysis should include PID analysis to check detector
performance (such as electron efficiency and pion rejection of lead
glass as functions of dispersive position x, and of Gas cherenkov as a
whole).
- Set up Pan Analysis framework, with Pan(da-pen)guin - Bob, Mark, Xiaoyan, Kai
- setup blinding (Kent and Mark know how to do it).
- Update EPICS and runstart/stop scripts for both DAQs - Bob, Rupesh.
- Followup on blinding - Xiaochao in contact with Kent and Mark.
- WAC analysis - Bob, with help from Mark.
- Day 1, 10/29, Thursday
- De-install HAPPEX detector from both left and right arms - Dustin, Rupesh.
- Install S1, gas cherenkov, lead glass on Left arm - Techs, with help from Ramesh and Dustin [expect to finish in one day]
- Warm up target - Dave Meekins
- Compton work in parallel - Michel, Alexandre
- The following can be done on Right arm in parallel:
- Understand BCM cabling & sources of noise - Xiaoyan, Kai
- FADC: Timing w/ cosmics, put in physical signals - Kai, with help from Ramesh
- Day 2, 10/30, Friday
- Cannot install right arm detectors today because the crane is broken;
- Install cables for lead glass, cherenkov and S1 on the Left arm - Ramesh, Xiaoyan, Kai, Diancheng
- Setup triggers for Left arm - Ramesh
- The following can be done as soon as left arm is all set:
- Left HRS pvdis DAQ checkout, comic runs, check all fbTDC and scaler outputs - Ramesh, Xiaochao
- Left HRS detector checkout, comic runs - Vince, Jin
- Establish correspondance between ADC channel and discriminator thresholds for left arm - Kai, Ramesh
- The following can be done on Left arm in parallel:
- Understand BCM cabling & sources of noise - Xiaoyan, Kai
- FADC: Timing w/ cosmics, put in physical signals - Kai, with help from Ramesh
- Switch target loop 3 from hydrogen to deuterium, switch Al dummy target - Dave Meekins
- Compton work in parallel
- Day 3, 10/31, Saturday
- Fix crane, bogies for the spectrometer - Techs;
- close up target chamber - Techs;
- Finish left arm and prepare for cosmic tests.
- Left HRS pvdis DAQ checkout, comic runs, check all fbTDC and scaler outputs - Ramesh, Xiaochao
- Left HRS detector checkout, comic runs - Vince, Jin
- Establish correspondance between ADC channel and discriminator thresholds for left arm - Kai, Ramesh
- BCM copies check: focus d1 and d3 - Kai
- Prepare trigger on right arm
- Techs fix the crane by 5pm
- Day 4, 11/01, Sunday
- continue left arm checkout and software work;
- Day 5, 11/02, Monday
- Install S1, gas cherenkov, lead glass on Right arm - Techs with help from Dustin [expect to finish in two days]
- Following detector installation, install cables for lead glass, cherenkov and S1 on the Right arm - Ramesh, Xiaoyan, Kai, Diancheng
- continue left arm checkout:
- Left HRS pvdis DAQ checkout, comic runs, check all fbTDC and scaler outputs - Ramesh, Xiaochao
- Left HRS detector checkout, comic runs - Vince, Jin
- Establish correspondance between ADC channel and discriminator thresholds for left arm - Kai, Ramesh
- start/continue other checkout, on both HRS:
- Some pulser test to make sure all connections are okay (? really, all connections? that will take years) - Ramesh with help from Diancheng and other students
- Understand BCM cabling & sources of noise - Xiaoyan, Kai
- FADC: Timing w/ cosmics, put in physical signals - Kai, with help from Ramesh
- Compton work in parallel
- Day 6, 11/3, Tuesday
- Continue detector installation on Right arm - Techs
- Continue installing cables for lead glass, cherenkov and S1 on the Right arm - Ramesh, Xiaoyan, Kai, Diancheng
- The following should be done as soon as Right arm is all set:
- Right
HRS pvdis DAQ checkout, comic runs, check all fbTDC and scaler outputs
(mostly double-check, since these were working before) - Ramesh, Xiaochao
- Right HRS detector checkout, comic runs - Vince, Jin
- Double
check correspondance between ADC channel and discriminator thresholds
for Right arm, compare with numbers from June as shown here - Kai, Ramesh
- Right HRS detector checkout, comic runs - Vince, Jin
- Compton work in parallel
- If this is the last day, then should do the following in parallel of items above:
- Cool down target (day shift) - Dave Meekins
- Finish trigger setup for Right arm (mostly double-checking) - Ramesh
- Setup PVDIS discriminator threshold, check signal widths - Ramesh and students.
- Survey of spectrometer angles - Ed in contact with survey group
- wrap up everything, prepare for Hall lock down!
- Beam tune starting Tuesday evening
- Day 7, 11/4, Wednesday (possible)
- Finish cable installation and cosmic/detector checkout on Right arm - Ramesh, Xiaoyan, Kai, Diancheng
Checklist:
INSTALLATION - Jack, Ramesh, Dustin, etc
remove HAPPEX detectors
install S1, LG, Cerenkov
Jack says he needs some experienced (postdoc) help
DAQ / Trig -- Ramesh plus students
Restore and make connections
Pulser Tests
HRS: Cosmics checkout of detectors
Fix tagger - Diancheng
Understand BCM cabling & sources of noise - Xiaoyan, Kai
FADC: Timing w/ cosmics, put in physical signals - Kai
Can we exercise the deadtime measurments ?
SOFTWARE
Set up Podd Analysis framework - Ramesh, Vince, Jin
Set up Pan Analysis framework - Bob, Mark, Xioayan, Kai
Update EPICS and runstart/stop scripts for both DAQs
COMPTON
Work to reduce pickup noise - Michel, Charles
Possible changes to shielding - Alexandre