PVDIS Switchover Run Plan Oct. 29-Nov. 1, 2009
DRAFT

Run Coordinator: Paul Reimer
Cell phone: (757)  876-1787     Pager:  (757) 584-5411


Things to do during switchover, including person in charge, [estimated time], and planned time. Note: almost all items can be moved earlier or later depending on how fast we proceed. Please keep in contact with others and the RC to facilitate your work.

Checklist:

INSTALLATION - Jack, Ramesh, Dustin, etc
   remove HAPPEX detectors
   install S1, LG, Cerenkov
   Jack says he needs some experienced (postdoc) help

DAQ / Trig  -- Ramesh plus students
   Restore and make connections
   Pulser Tests
   HRS: Cosmics checkout of detectors
   Fix tagger - Diancheng
   Understand BCM cabling & sources of noise - Xiaoyan, Kai
   FADC: Timing w/ cosmics, put in physical signals - Kai
   Can we exercise the deadtime measurments ?

SOFTWARE
   Set up Podd Analysis framework - Ramesh, Vince, Jin
   Set up Pan Analysis framework - Bob, Mark, Xioayan, Kai
   Update EPICS and runstart/stop scripts for both DAQs

COMPTON
   Work to reduce pickup noise - Michel, Charles
   Possible changes to shielding - Alexandre