# Days since HAPPEX end | Plan | Date (estimate) | Day of week | % towards completion | Beam Energy | Left HRS angle | Left HRS p0 | time | Right HRS angle | Right HRS p0 | time | surveys or tech support needed | Notes |
1 | switchover | 10/29/09 | Thursday | ||||||||||
2 | switchover | 10/30/09 | Friday | install DAQ | |||||||||
3 | switchover | 10/31/09 | Saturday | install DAQ | |||||||||
4 | switchover | 11/01/09 | Sunday | 12.9 (DIS#1) | -3.66 | 20 (DIS#2) | -2.63 | DAQ checkout | |||||
5 | switchover | 11/02/09 | Monday | both HRS angles, Left before 11/25, right before 12/19 | |||||||||
6 | commissioning | 11/03/09 | Tuesday | 6.068 | 12.9 | -3.66 | 20.0 | -2.63 | |||||
7 | commissioning | 11/04/09 | Wednesday | ||||||||||
8 | commissioning | 11/05/09 | Thursday | ||||||||||
9 | commissioning | 11/06/09 | Friday | ||||||||||
10 | 11/07/09 | Saturday | 0.00 | ||||||||||
11 | First day of actual production | 11/08/09 | Sunday | 2.27 | 6.068 | 12.9 | -3.66 | 432 ->384 hours | 20.0 | -2.63 | 1507->1368 hours | ||
12 | 11/09/09 | Monday | 4.55 | 18->16 days | 63->57 days | ||||||||
13 | 11/10/09 | Tuesday | 6.82 | LD2 | LD2 | ||||||||
14 | 11/11/09 | Wednesday | 9.09 | 15 hours 50uA on Al dummy (4% of LD2 time for a 0.4% endcap error) | 55 hours 50uA on Al dummy (4% of LD2 time for a 0.4% endcap error) | ||||||||
15 | 11/12/09 | Thursday | 11.36 | ||||||||||
16 | 11/13/09 | Friday | 13.64 | ||||||||||
17 | 11/14/09 | Saturday | 15.91 | ||||||||||
18 | 11/15/09 | Sunday | 18.18 | ||||||||||
19 | 11/16/09 | Monday | 20.45 | ||||||||||
20 | 11/17/09 | Tuesday | 22.73 | ||||||||||
21 | 11/18/09 | Wednesday | 25.00 | ||||||||||
22 | 11/19/09 | Thursday | 27.27 | 5 hours on Al dummy done, 10 hours to go | 5 hours on Al dummy done, 50 hours to go | ||||||||
23 | 11/20/09 | Friday | 29.55 | ||||||||||
24 | 11/21/09 | Saturday | 31.82 | ||||||||||
25 | 11/22/09 | Sunday | 34.09 | 9 hours on Al dummy done, 6 hours to go | 9 hours on Al dummy done, 46 hours to go | ||||||||
26 | Positron Running, spot change | 11/23/09 | Monday | 36.36 | 12.9 | +3.66 then change to -3.66 | data taking at +3.66 is >5 hours, now up to 9 hours | +2.63 then change to -2.63 | data taking at +2.63 is >5 hours, now up to 9 hours | tech changes polarity on both arms starting 12noon, then change them back 8am on Tuesday. | |||
27 | 11/24/09 | Tuesday | 38.64 | ||||||||||
28 | 11/25/09 | Wednesday | 40.91 | 13 hours on Al dummy, 2 hours to go | 42 hours on Al dummy, 2 hours to go | ||||||||
29 | 11/26/09 | Thursday, Thanksgiving Day | 43.18 | ||||||||||
30 | 11/27/09 | Friday | 45.45 | ||||||||||
31 | 11/28/09 | Saturday | 47.73 | ||||||||||
32 | 11/29/09 | Sunday | 50.00 | ||||||||||
33 | 11/30/09 | Monday | 52.27 | ||||||||||
34 | Transverse Running | 12/01/09 | Tuesday | 54.55 | 8 hours setup plus 16 hours data taking | invasive to Hall B, need MCC support | could be done earlier, it depends on MCC and Hall B. | ||||||
35 | Mini spin dance plus Left arm kinematics change | 12/02/09 | Wednesday | 56.82 | 14.0 (RES#7) | -4.00 (could not reach) | |||||||
36 | 12/03/09 | Thursday | 59.09 | 15.0 (RES#7 modified) | -3.66 | 23 hours | |||||||
37 | 12/04/09 | Friday | 61.36 | 20.0 (DIS#2) | -2.63 | LHRS new angle (20 deg) | angle change could take one full shift | ||||||
38 | 12/05/09 | Saturday | 63.64 | ||||||||||
39 | 12/06/09 | Sunday | 65.91 | ||||||||||
40 | 12/07/09 | Monday | 68.18 | ||||||||||
41 | 12/08/09 | Tuesday | 70.45 | ||||||||||
42 | 12/09/09 | Wednesday | 72.73 | ||||||||||
43 | 12/10/09 | Thursday | 75.00 | ||||||||||
44 | 12/11/09 | Friday | 77.27 | ||||||||||
45 | 12/12/09 | Saturday | 79.55 | ||||||||||
46 | 12/13/09 | Sunday | 81.82 | ||||||||||
47 | 12/14/09 | Monday | 84.09 | ||||||||||
48 | 12/15/09 | Tuesday | 86.36 | ||||||||||
49 | 12/16/09 | Wednesday | 88.64 | 6.068 | 20.0 (DIS#2) | -2.63 | 20 (DIS#2) | -2.63 | |||||
50 | Pass Change | 12/17/09 | Thursday | 90.91 | 4.868 | move both HRS to 12.9 deg | 12.9 (RES#5) | -3.10 | 87 hours | left HRS angle survey and both spectrometer move to 12.9 deg. | |||
51 | Resonance Running | 12/18/09 | Friday | 93.18 | 4.868 | 12.9 (RES#3) | -4.00 | 31 hours | |||||
52 | 12/19/09 | Saturday | 95.45 | 4.868 | 12.9 (RES#4) | -3.55 | 57 hours | ||||||
53 | 12/20/09 | Sunday | 97.73 | 4.868 | |||||||||
54 | 12/21/09 | Monday | 100.00 | 4.868 | target warm up at the end of day, for endcap rate measurement? | ||||||||
55 | beam stops at 7am | 12/22/09 | Tuesday | 4.868 | |||||||||
56 | beam study | 12/23/09 | Wednesday | ||||||||||
57 | down | 12/24/09 | |||||||||||