    Log entry time 15:56:16 on July 17, 2000

    Entry number 46136

    keyword=Beam Time Accounting
    Hall A

    7/17/2000 0800-1600
    Experiment #: ndelta
    Shift Leader: Arun Saha
    Shift Workers: Zhengwei chai TO, Franco Garibaldi

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    1 58 0 0 0 0 0 0 1.96666666666667
    Beam Available
    but Not in Use
    0 0 0 0 0 0 0 0 0
    Beam Not Available
    or Unacceptable
    0 2 1 1 1 1 1 1 6.03333333333333
    Accelerator Con-
    figuration Chage
    0 0 0 0 0 0 0 0 0
    Experiment
    Ready
    1 1 1 1 1 1 1 1 8
    Planned Config-
    uration Change
    0 0 0 0 0 0 0 0 0
    Unplanned
    Experiment Down
    0 0 0 0 0 0 0 00
    Hall not
    ready reasons
    Target 0 0 0 0 0 0 0 0 0
    HRSe 0 0 0 0 0 0 0 0 0
    HRSh 0 0 0 0 0 0 0 0 0
    Data Ac 0 0 0 0 0 0 0 0 0
    Other 0 0 0 0 0 0 0 0 0

    Comments: No beam since 10am.

    Data Entry by: Z. Chai