0000 | 0100 | 0200 | 0300 | 0400 | 0500 | 0600 | 0700 | Total Time | |
---|---|---|---|---|---|---|---|---|---|
Acceptable Beam in Use | .75 | .7 | 0 | .66 | .75 | .6 | .87 | 1 | 5.33 |
Beam Available but Not in Use | .25 | .3 | 1 | .34 | 0 | .4 | 0 | 0 | 2.29 |
Beam Not Available or Unacceptable | 0 | 0 | 0 | 0 | .25 | 0 | .13 | 0 | 0.38 |
Accelerator Con- figuration Chage | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Experiment Ready | 1 | .7 | 0 | .66 | 1 | .6 | 1 | 1 | 5.96 |
Planned Config- uration Change | 0 | 0 | 0 | 0 | 0 | .4 | 0 | 0 | 0.4 |
Unplanned Experiment Down | 0 | .3 | 1 | .34 | 0 | 0 | 0 | 0 | 1.64 |
Hall not ready reasons | |||||||||
Target | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSe | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
HRSh | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Data Ac | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Other | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Comments: had to reset trigger supervisor in Hall A detector hut 2:00am--1.5 hr delay
Data Entry by: Crawford