    Log entry time 02:55:03 on June 1,2002

    Entry number 4340

    keyword=target

    After numerous short sieve slit runs at different target heights, it was determined that the target ladder was offset about 4 mm. Dave Meekins adjusted the settings in the target control program, so operators do not need to put in offset values when changing the target. Now, when we ran with the optics target we get a much nicer sieve slit pattern.