    KIN 5.17


    4:33: Beam back. The beam fluctuates throughout the run (Run 3000)
    4:59: Run 3001: problem with fast feed back (FFB). Beam position fluctuates
    throughout the run

    5-6: MCC working on FFB (Run 3002 when beam back)
    6-6:50: Did measurement of intrinsic spot size
    Results: horizontal: 133 um
    vertical: 180 um
    7:00-7:30: Finish 5.17, 0°
    7:30-8:00: Runs 3008, 3009 at 270°

    KIN 5.18


    8:00: NMR, EPR=40.6%
    8:25: Run 3010: Empty Reference Cell (10 uA)
    8:40: Run 3011/3012:
    Nitrogen Reference Cell (140 psig) at 3 uA with PS1/PS2=10/10
    9:05: Start Helium running at 0°
    Need approximately 10.6 M events
    Runs 3014, 3015, 3016, 3017, 3018, 3019, 3020, 3021, 3022

    KIN 5.19

    Here comes the night shift.