    keyword=Hall A status for beam studies

    It looks that there was some kind of misunderstanding about the spectrometer. RC told me that it needed to be off for the tests ( physically turned off by a tech ) at the PD request. But this would need an access which was not planned. I turned all magnetic fields from the spectrometers to 0 just in case it might interfere with the tests. DVCS detectors is off and we are on empty target. We are ready for the tests and I told MCC to go ahead with their test since about 8:15.