    Log entry time 09:09:29 on February 1, 2005

    Entry number 140529

    keyword=Beam Time Accounting
    
    	
    Hall A

    02/01/05 0800-1600
    Experiment #: e01015
    Shift Leader: Peter Monaghan
    Shift Workers:

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    0.620.000.000.000.000.000.000.000.62
    Beam Available
    but Not in Use
    0.200.000.000.000.000.001.001.002.20
    Beam Not Available
    or Unacceptable
    0.180.000.000.000.000.000.000.000.18
    Accelerator Con-
    figuration Change
    0.001.001.001.001.001.000.000.005.00
    Experiment
    Ready
    0.800.000.000.000.000.000.000.000.80
    Planned Config-
    uration Change
    0.201.001.001.001.001.001.001.007.20
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: First hour was data taking for SRC experiment and then installation work for a GEN test for the rest of the shift. Numbers for 10am - 4pm are based on the accelerator white board and the work being done in hall A.

    Data Entry by: Peter Monaghan