    User name jroche

    Log entry time 19:55:03 on August 28, 2005

    Entry number 153675

    keyword=vertical polarization measurement scheduled for Monday and Tuesday

    In order to understand the difference between the asymmetry measured by detector 1 (left arm) and detector 3 (left arm), we will be taking data with the beam polarized vertically starting Monday during the day.

    6-8 hours are needed to established beam delivery in this configuration. 2-3 hours are needed to reverse from vertical to longitudinal polarization. The exact duration of this test depend on what the detectors will be measuring, but nominally the back out form vertical polarization is scheduled for Tuesday.

    Attached is the schedule for next week, including the non-production tests that we plan to do before the Labor day shutdown.

    Kudos to Kent who got us this much needed time !

    A copy of this log entry has been emailed to: paschke@jlab.org, armd@jlab.org, rom@jlab.org