    Log entry time 01:19:32 on July27,2006

    Entry number 175501

    keyword=Going to do Radiator Commissioning next

    Ron G. is on his way in to commission the radiator.
    We cannot proceed with the planned beam calibration activities because of the just-broken Harp 6...can't do BPM calibration (bull's eye scan), nor spot_L calibration (harp scan through rastered beam) without the harp working.
    Next on the list: radiator commissioning!