    User name brads

    Log entry time 08:27:03 on July 30, 2006

    Entry number 176248

    This entry is a followup to: 176239

    keyword=Max time for each production setting is...?

    The total time for the #5 kinematics point is going to run ~16 hours using the numbers from the LEDEX beam time calculator. Is this OK, or should I be bound by the nominal 12 hours per point?

    A copy of this log entry has been emailed to: rgilman@physics.rutgers.edu, sarty@ap.stmarys.ca, strauch@sc.edu, brads@jlab.org