    Log entry time 16:06:27 on November 30, 2006

    Entry number 189583

    keyword=Beam Time Accounting
    Hall A

    11/30/06 0800-1600
    Experiment #: e04018
    Shift Leader: M. Petratos
    Shift Workers: G. Urciuoli, A. Camsonne

    08000900100011001200130014001500Total Time
    Acceptable Beam
    in Use
    0.000.000.000.000.000.000.000.000.00
    Beam Available
    but Not in Use
    0.000.000.000.000.000.000.000.000.00
    Beam Not Available
    or Unacceptable
    1.001.001.001.001.001.001.001.008.00
    Accelerator Con-
    figuration Change
    0.000.000.000.000.000.000.000.000.00
    Experiment
    Ready
    1.001.001.001.001.001.001.001.008.00
    Planned Config-
    uration Change
    0.000.000.000.000.000.000.000.000.00
    Unplanned
    Experiment Down
    0.000.000.000.000.000.000.000.000.00
    Hall not
    ready reasons
    Target0.000.000.000.000.000.000.000.000.00
    Data Acq0.000.000.000.000.000.000.000.000.00
    Other0.000.000.000.000.000.000.000.000.00
    HRSL0.000.000.000.000.000.000.000.000.00
    HRSR0.000.000.000.000.000.000.000.000.00
    HALL_OFF0.000.000.000.000.000.000.000.000.00

    Comments: Entire shift was on beam studies by Machine crew. Target is operational, but under close monitoring. At 4:00pm Dave Meekings is going downstairs for some checks.

    Data Entry by: Makis Petratos